Heat PumpASHPGSHPWSHPCISCISR14090CISR14240CISR14220VATNotice 708/6Zero RateEnergy Saving MaterialsMCSBUSUK TradesInvoice TemplateDepositsDomestic Reverse Charge

Heat pump invoice template UK (2026): ASHP, CIS and VAT

By InvoiceAdept Editorial7 September 2026Updated 7 September 202627 min read

A heat pump invoice has to explain what was surveyed, designed, first-fixed, installed, commissioned and handed over - not a vague "heat pump fitted" line. "Supply and install ASHP as agreed" does not tell a householder whether they got an air-source outdoor unit with a new cylinder and controls, a ground-source loop and indoor plant, a water-source package, radiator upgrades or underfloor as part of the same job, or electrics and making-good. It does not tell a main contractor's QS which plot, purchase order or M&E package to release. It does not tell a CIS contractor how much is labour and how much is the direct cost of the outdoor unit, cylinder, pipework, ground loop materials, radiators and controls you paid for.

Heat pumps are heating-system work, not a boiler swap brochure and not a full extension or orangery build. Mentions of a plumber, gas engineer, electrician or builder on this page are contrasts and cross-links - the subject here is the heat pump package (ASHP, GSHP or WSHP) with the pipework, emitters and controls that make it a working system. Soft landscaping or decking alone belongs elsewhere; keep planting and deck boards out of a heat-pump-only invoice unless they were part of the agreed package.

Who pays matters. Billing a private householder for a heat pump on their own home: normal invoice, no CIS. Billing a main contractor, developer or refurbishment principal for construction operations that include installing a heating system: often CIS. HMRC's CISR14090 is the lead reference for heat pump and heating-system work: Finance Act 2004 section 74(2)(c) covers installation of systems of heating (and other building services). Soften absolute claims - the facts of the contract matter. Under that manual, installation of a heating system is typically within scope when a contractor pays you; repair, maintenance, alteration or extension of an existing heating system is generally outside CIS; replacing a boiler as a component of an existing system can fall outside; a complete system replacement or a new install is in. When GSHP groundworks, trenches, boreholes or making-good sit in a preparatory or finishing package, CISR14240 can also be relevant. Soften if you only supply units with no install - CISR14220 keeps manufacture/delivery of building components alone outside CIS. Supply-plus-install can pull the whole payment into CIS (CISR14020 / CISR14030). Related fabric work (plant-room walls, floor openings) may still need a look under CISR14100, but for the heat pump itself lead with CISR14090. Private householders are not CIS contractors - see the public CIS overview.

VAT is different from decking and many other trade pages. For qualifying residential (and relevant charitable) installs of air-source, ground-source or water-source heat pumps, VAT Notice 708/6 sets a zero rate from 1 May 2023 to 31 March 2027 (then the treatment reverts toward the 5% reduced rate under the notice's framework - check the live notice nearer the time). Soften: the installer must meet the notice conditions; InvoiceAdept does not decide VAT status. Supply without install is usually standard-rated. Central heating where the heat pump is the principal element can be treated as a single zero-rated supply in the notice's worked examples (see Notice 708/6 example 3) when conditions are met. Never invent 0% for commercial, hospital or hotel installs that fall outside residential/charitable scope. Never reverse-charge a householder. Domestic reverse charge does not apply to zero-rated supplies.

This guide gives copy-paste fields, a labour/materials split for heat pump packages (including deposits before ordering units), stages from survey/design through first fix, unit install/commission and snag/handover, four worked examples and a practical treatment of CIS, VAT Notice 708/6 and domestic reverse charge. Figures are illustrative only, not UK market rates or a price list. InvoiceAdept does not decide CIS or VAT status and does not file CIS300, VAT returns, Making Tax Digital updates or Self Assessment to HMRC. It does not issue MCS certificates, Building Control certificates or Boiler Upgrade Scheme (BUS) grant paperwork.

Related templates: plumber, gas engineer, electrician, builder, deposit invoice, domestic reverse charge, how to invoice a UK client as a tradesperson and late payment rights. This page focuses on residential heat pump packages - ASHP outdoor unit plus indoor cylinder/controls, GSHP ground loops/boreholes, WSHP where relevant, radiator upgrades / underfloor as package lines, and electrics - not a stand-alone gas boiler swap as the main product.

Rules and links were checked for this guide on 7 September 2026. General information only, not tax, legal, Building Regulations, MCS, F-gas or grant advice. InvoiceAdept is from Tech Me Today Ltd, Companies House 15917255, ICO ZB944663.

In short

Start by identifying who pays you, which heat pump type you supplied or installed (ASHP / GSHP / WSHP), whether the job is a new system install or work on an existing heating system, whether units must be ordered before work starts, and whether the contract is supply-only or supply-and-install.

Private householder, own-home heat pump install: no CIS. The householder is not a CIS contractor. If VAT-registered and the install qualifies under Notice 708/6 for residential (or relevant charitable) energy-saving materials / heat pumps, the zero rate can apply from 1 May 2023 to 31 March 2027 when notice conditions are met - then check the live notice for the post-March 2027 position (framework points back toward 5%). Show survey/design, first-fix pipe/electrics/groundworks, outdoor unit, cylinder/controls, emitters, commission, snag and any BUS voucher narrative clearly. Do not invent 0% for a commercial plant room outside scope. Never reverse-charge a householder.

Heat pump package for a CIS contractor: typically within CIS when a contractor pays you for installation of a heating system (CISR14090). Soften: repair/maintenance/alteration/extension of an existing heating system is generally outside; component boiler swaps can be outside; complete system replacement / new install is in. Cite CISR14240 when GSHP groundworks or making-good sit inside a preparatory or finishing package. Split labour from materials at direct cost (CISR15060 / CISR15090). For heat pump units and cylinders purchased complete, materials are usually the purchase cost; labour is the install, pipework, electrics and commission.

Manufacture and delivery of units only (no install): generally outside CIS (CISR14220). A mixed contract that supplies the unit and includes installation can pull the whole contract into CIS (CISR14020 / CISR14030).

VAT zero rate (Notice 708/6): only when residential/charitable and notice conditions are actually met, for the window to 31 March 2027. Supply-only is usually standard-rated. Never reverse-charge a householder. Domestic reverse charge does not apply to zero-rated supplies.

Take a deposit before ordering heat pump outdoor units, cylinders or GSHP loop materials if your terms require one. Number and invoice that deposit. Then use recognisable stages: survey/design, first fix, unit install/commission, snag/handover. Keep variations for extra radiators, underfloor zones or buffer tanks separate from the agreed package.

Use the invoice generator for a first invoice. InvoiceAdept Free is £0 for five invoices per month. Pro is £7.99 excl VAT and includes WhatsApp send. Pro+ is £12.99 excl VAT and includes CIS. Stripe's own fees apply (UK cards 1.5%+20p), but InvoiceAdept adds no platform fee.

Who this heat pump invoice template is for

This template is for UK heat pump installers, heating engineers, plumbers and M&E subcontractors who deliver ASHP, GSHP or WSHP packages as a defined product, and for builders who include heat pumps in residential packages and need readable invoices for householders, landlords, contractors and housing clients. It covers the paperwork pattern, not a price list and not an MCS, Building Control or BUS document.

  • Heat pump installers (air-source, ground-source, water-source)

  • Heating engineers and plumbers who design and install heat pump systems as a defined package

  • Gas engineers transitioning or running hybrid packages who still need clear heat-pump lines

  • Electricians billing dedicated circuits, consumer-unit upgrades or controls as part of a package (or separately)

  • Groundworkers trenching or drilling for GSHP loops as part of a heat pump package

  • Builders who include heat pumps in residential packages alongside extensions or new plots

  • Subcontractors to main contractors on residential heating / M&E packages

  • Sole traders and limited companies who need CIS and VAT lines that match the payer

If your day job is a stand-alone gas boiler swap with no heat pump brief, a pure electrical rewire without a heat pump, or fabric-only building work, use those related guides and come back here for heat-pump-specific lines (outdoor unit, cylinder, ground loop, emitters, controls, commission and Notice 708/6 VAT notes).

Three heat pump jobs, three invoices

These three jobs can use similar kit but need different invoice logic.

Domestic householder heat pump

Contractor heat pump package

Materials-only / supply-only caution

Customer on invoice

Private householder

Builder, developer or M&E principal

Builder, merchant customer or householder

Contract

Survey, design, first fix, unit install, cylinder/controls, emitters, commission, snag

Heating / M&E package to named plots or addresses

Supply outdoor unit / cylinder / loop materials delivered; no install

CIS

No. Householder is not a CIS contractor.

Often within CIS for installation of a heating system - CISR14090; CISR14240 if GSHP groundworks/prep; soften if only repair of existing system

Generally outside CIS (CISR14220) - unless mixed with install

Labour/materials

Helpful for clarity

Essential for correct deduction; units/cylinder/loop kit at direct cost

Materials supply lines; no CIS labour block

VAT if registered

Often 0% under Notice 708/6 for qualifying residential install to 31 Mar 2027 when conditions met; else check notice

Normal VAT, zero rate if still qualifying, or reverse charge only on standard-rated eligible supplies

Usually standard-rated supply without install

Key references

Notice 708/6; public CIS guide

CISR14090; CISR14240; CISR15060/15090

CISR14220; CISR14020 / CISR14030 if later install added

What often bounces it

"Heat pump done" with no type, capacity, stage or deposit credit; inventing 0% for commercial

Missing UTR, plot/PO, labour/material split; claiming free-issue unit as your materials; CIS on pure repair of existing system without checking CISR14090

Treating supply-only as CIS labour; then adding install under same contract without revisiting mixed rules

A main contractor can be the CIS contractor even when the finished system serves a tenant or homeowner. If the builder engages you, your invoice is to that builder. That contractor-to-subcontractor payment is the one to test. If the householder hires and pays you directly, the householder invoice has no CIS.

What heat pump work belongs on the invoice

Name the work so a QS, householder or future buyer can see what was actually installed.

Line group

Typical inclusions

Do not bury here

Survey / design

Heat loss, emitter check, electrical capacity notes, siting of outdoor unit, loop design for GSHP

A silent "design fee" with no visit or deliverable

First fix pipe / electrics

Flow/return routes, condensate, dedicated circuit, cable, consumer-unit work if in package

Whole-house rewire unrelated to the heat pump

Groundworks (GSHP)

Trenches, horizontal loops, boreholes, manifold chambers, backfill, making good

Soft landscaping planting unless agreed

Outdoor / source unit

ASHP outdoor unit, WSHP plant, or GSHP ground array materials at direct cost

Free-issue kit the main contractor supplied

Indoor plant

Cylinder, buffer, low-loss header, controls, wiring centre, sensors

MCS certificate (invoice is not the certificate)

Emitters

Radiator upgrades, fan coils, underfloor manifolds and circuits if in package

A separate bathroom remodel billed as "emitters"

Commission / handover

Flush, fill, inhibitor, commissioning checks, user handover

BUS grant paperwork as if InvoiceAdept issued it

Waste / making good

Skip, old boiler removal if included, floor/wall making good

Van stock you did not buy for this address

Variations

Agreed extras coded V01, V02 with written approval

Silent bumps inside "additional heat pump works"

ASHP jobs need outdoor unit model/capacity, cylinder type and emitter scope on the description. GSHP jobs still need loop type (horizontal / borehole), array length or borehole count if quoted, and indoor plant. WSHP needs the water source arrangement as narrative. F-gas / refrigerant handling belongs in your compliance process - the invoice is not the F-gas register.

What a UK heat pump invoice must include

GOV.UK is narrower than most blogs. You must give a VAT invoice by law when both you and the customer are VAT-registered. If you are not registered, keep numbered records of what you charged - which is also how you get paid.

  • A unique identification number

  • Your name (or company name), address and contact information

  • The customer's name and address

  • A clear description of what you are charging for (address, ASHP/GSHP/WSHP, capacity, stage)

  • The date the goods or service were provided (supply date) and the date of the invoice

  • The amount being charged, the VAT amount if applicable (including 0% with the right narrative when Notice 708/6 applies), and the total amount owed

Sole trader with a trading name: show your own name and a serviceable address. Limited company: registered name, company number and registered office. The VAT registration threshold is £90,000, not the stale £85,000 figure. For a heat pump invoice, a clear description is what gets you paid, so name the site address, system type, approximate capacity, key plant (outdoor unit / cylinder / loop) and stage (deposit / first fix / install / completion).

CIS lines (UTR, labour, materials, rate, deduction, net payable) belong when a contractor is paying you under the scheme - not on a private householder job. Domestic reverse charge wording belongs only when the VAT reverse-charge tests are actually met between VAT-registered construction businesses on standard-rated supplies - never on a householder bill, and not on zero-rated Notice 708/6 lines. See domestic reverse charge.

Copy-paste heat pump invoice fields

Use these as a checklist when you raise the PDF or app invoice.

Field

Example (illustrative)

Invoice number

HP-2026-0142

Invoice date

7 September 2026

Supply / tax point

5 September 2026 (or deposit date if deposit)

From

Your legal name / Ltd name, address, company number if Ltd, VAT number if registered

Bill to

Householder name + site address, or contractor legal name + accounts email + PO

Site address

12 Example Road, Town, Postcode (if different from bill-to)

PO / plot

PO-7781 / Plot 14 (contractor jobs)

Description

ASHP outdoor unit approx 8 kW with new cylinder and controls; radiator upgrades to 8 emitters; dedicated circuit; commission and handover at [address]

Labour

Design support, first fix, install, electrics, commission labour (split for CIS)

Materials

Outdoor unit, cylinder, pipe, fittings, radiators, controls at direct cost

Deposit credit

Less deposit HP-2026-0138 £2,500 (illustrative)

VAT

0% Notice 708/6 if qualifying residential install and conditions met; else as applicable; never invent commercial 0%

Due date

21 September 2026

Payment

Sort code / account / reference, or Stripe card link

CIS block

Only if contractor-paid and CIS applies: UTR, CIS base, rate, deduction, net

For the first invoice habit and field checklist, see how to invoice a client UK tradesperson. For deposits before ordering units, see the deposit invoice template.

Sole trader versus limited company

Sole trader

Limited company

Name on invoice

Your own name (trading name optional alongside)

Registered company name

Company number

Not applicable

Show Companies House number

Registered office

Serviceable address

Registered office on invoice / letterhead practice

VAT

Only if registered - threshold £90,000

Same

CIS

Same scheme rules if a contractor pays you for in-scope construction ops

Same

InvoiceAdept

Works for both

Works for both

Do not invent a Ltd presentation if you are still a sole trader. Do not omit the company number on Ltd invoices when customers and accounts teams expect it.

Labour versus materials for heat pump CIS

On a householder invoice the split is courtesy and clarity. On a contractor invoice it is the CIS calculation when the work is in scope. Start with the gross, take off VAT, then take off the direct cost of materials you paid for. What is left is broadly the CIS base at 20%, 30% or 0% after verification.

Line type

What belongs there

What does not

Labour

Survey/design labour, first-fix pipe/electrics, groundworks labour, unit install, cylinder, emitter upgrades, commission, snag

A mark-up you wish was kit

Materials

What you paid this job: outdoor unit, cylinder, buffer, pipe, fittings, loop pipe, radiators, controls, electrical accessories, merchant tickets on file

Free-issue unit from the main contractor; van stock you did not buy for this address

Hire

Third-party scaffold, lifting, drilling rig hire for this address, ticket on file

A notional hire on tools you own

Variation

Agreed extra radiators, underfloor zone, buffer tank or electrics upgrade, coded V01, V02

A silent bump inside "additional heat pump"

Two habits cost money: one lump "heat pump £12,000" (CIS on the outdoor unit as well if you are under CIS) and stuffing mark-up into materials so CIS looks smaller. Heat pump units purchased as complete plant are usually materials at purchase cost; labour is the install and commission. Free-issue plant is not your material.

What heat pump job types to describe

Job type

Description cues

CIS / VAT watch-outs

New ASHP to occupied home

Capacity, outdoor unit siting, cylinder, emitters, electrics, commission

Householder: no CIS; often Notice 708/6 0% if qualifying to Mar 2027

GSHP with horizontal loops

Loop length, trenches, manifold, indoor plant, making good

CISR14240 may sit with groundworks when contractor-paid; VAT still Notice 708/6 if qualifying

GSHP boreholes

Borehole count/depth as quoted, header, indoor plant

Deposit before drilling/materials; CIS if contractor-paid install

WSHP package

Water source arrangement, plant, emitters

Soften site-specific consents; invoice is not the consent

Hybrid / ASHP with existing boiler retained

What is new vs retained; controls integration

Soften CIS if work is alteration of existing system - CISR14090 nuances

Radiator upgrade package with ASHP

Emitter count, sizes, TRVs, balancing

Keep as clear package lines

Underfloor with heat pump

Zones, manifolds, screed notes if in package

Do not merge unrelated floor finishes unless one package

Supply-only outdoor unit

Model, delivery address, no install

Generally outside CIS (CISR14220); usually standard-rated VAT

Repair / service of existing heat pump

Fault, parts, labour

Often outside CIS under CISR14090 repair/maintenance framing - test facts

Deposits and stages for multi-day heat pump jobs

A same-day minor control swap can be one invoice. An ASHP with cylinder, electrics and radiator upgrades - or a GSHP with groundworks - is not.

1. Deposit: before you order the outdoor unit, cylinder or GSHP loop materials. Invoice when you take it and state the percentage or fixed sum. See deposit invoice template. 2. Survey / design: heat loss, emitter schedule, electrical notes, siting and (for GSHP) loop design deliverables if billed as a stage. 3. First fix: pipe routes, electrics, groundworks/trenches/boreholes complete, ready for plant. 4. Unit install / commission: outdoor unit or ground array connected, indoor plant, emitters, flush, commission, user handover. 5. Snag / handover: agreed snags closed, balance less any agreed retention, plus variations approved in writing.

Retention is not a deposit. Deposit is money you take before or during. Retention is money held after completion against snagging. Show full value, retention withheld and release date, then invoice retention when it falls due. A deposit you receive is a VAT tax point for that amount on the day it lands if you are registered - apply the correct rate (including 0% when Notice 708/6 genuinely applies to that supply).

Stage

Typical trigger

What the invoice should say

Deposit

Quote accepted / plant ordered

Deposit X% on ASHP package at [address]; unit/cylinder order

Survey / design

Design pack issued

Stage - heat loss, emitter schedule, siting notes

First fix

Pipe/electrics/groundworks ready

Stage - first fix pipe, dedicated circuit, trenches/loops as applicable

Install / commission

System running, commissioned

Stage - unit install, cylinder, emitters, commission; less deposit credit

Snag / handover

Snags closed

Final balance / snag close; BUS/MCS narrative only if factual

CIS: why heat pump installs are often within the scheme when contractor-paid

For contractor-paid work, start with CISR14090: installation of systems of heating (and other building services) under FA04/S74(2)(c). Soften absolute claims - the facts of the contract matter.

Key nuances from that manual (paraphrased carefully):

  • Installation of a heating system is typically within CIS when a contractor pays you.

  • Repair, maintenance, alteration or extension of an existing heating system is generally outside CIS.

  • Replacing a boiler (or similar component) as part of an existing system can fall outside.

  • A complete system replacement or a new install is in.

When GSHP trenches, boreholes, manifolds or making-good sit in a preparatory or finishing package, CISR14240 may also sit in the analysis. Related fabric openings or plant-room works can still touch CISR14100, but lead with CISR14090 for the heating system itself.

Situation

Typical CIS reading (always test facts)

Private householder pays you for their own-home heat pump

No CIS - householder is not a CIS contractor

Main contractor pays you to install new ASHP/GSHP systems on plots

Often within CIS as heating-system installation (CISR14090)

You only deliver outdoor units to site, no install

Generally outside (CISR14220)

You supply the unit and install under one contract

Mixed contract risk - CISR14020 / CISR14030 can pull the whole payment in

Free-issue unit from contractor; you labour only

Labour is CIS base when in scope; free-issue is not your materials

Call-out repair on an existing heat pump for a contractor client

Often outside under repair/maintenance framing in CISR14090 - still test facts

GSHP groundworks as preparatory package under a contractor

CISR14240 may apply alongside the heating install analysis

Rates after verification: 20% if registered net, 30% if not verified, 0% with gross payment status. Show UTR, labour, materials, rate, deduction and net payable. That printout is not a CIS300 - the contractor files it. InvoiceAdept does not file CIS300.

Deemed contractors (non-construction businesses) use a construction-spend test of more than £3 million in the 12 months since the first payment - not a £1 million myth. Mainstream construction businesses register when they pay subcontractors for construction work. See GOV.UK CIS.

VAT Notice 708/6: zero rate for qualifying heat pump installs

This is the section that differs most from decking and many other InvoiceAdept money pages. Read it slowly.

If you are not VAT-registered, do not charge VAT. If you are registered, check whether the supply is a qualifying install of energy-saving materials / heat pumps under VAT Notice 708/6.

Careful framing (always soften - InvoiceAdept does not decide VAT status):

  • From 1 May 2023 to 31 March 2027, qualifying residential (and relevant charitable) installs of air-source, ground-source and water-source heat pumps can be zero-rated when notice conditions are met.

  • After 31 March 2027, the notice framework points back toward the 5% reduced rate - check the live GOV.UK notice nearer the time rather than inventing a permanent 0%.

  • Supply of heat pump equipment without installation is usually standard-rated.

  • Where a heat pump is the principal element of a central heating system, Notice 708/6 example 3 supports treating the package as a single zero-rated supply when conditions are met - soften; match the notice, do not stretch it.

  • Never invent 0% for commercial, hospital, hotel or other installs that fall outside residential/charitable scope.

  • Never reverse-charge a householder.

  • Domestic reverse charge does not apply to zero-rated supplies.

Job

VAT rate if you are registered (typical starting point)

Qualifying residential ASHP/GSHP/WSHP install (Notice 708/6 conditions met), to 31 Mar 2027

Often 0%

Same job after 31 Mar 2027

Check live notice - framework toward 5%

Supply of outdoor unit only, no install

Usually 20%

Commercial / hotel / hospital plant outside residential/charitable scope

Do not invent 0% - usually standard-rated unless another relief truly applies

Design-only fees with no install

Soften - often outside the install relief; get advice

Domestic reverse charge on standard-rated CIS construction between eligible parties

Show VAT, do not add it to the amount they pay - and remember reverse charge does not apply to zero-rated lines

Householder customer

Never reverse-charge

Never tell a commercial client their plant-room ASHP is "VAT free because heat pumps are zero-rated" without checking scope. Never reverse-charge a private individual.

Supply-only versus supply-and-install

Contract shape

CIS (contractor-paid)

VAT (if registered)

Supply outdoor unit / cylinder delivered, no install

Generally outside (CISR14220)

Usually standard-rated

Supply and install under one contract

Mixed rules - CISR14020/14030 can pull whole payment into CIS when install is in scope

Often Notice 708/6 analysis if residential qualifying install

Install labour only; free-issue plant

Labour in CIS base when installation in scope (CISR14090)

Still test Notice 708/6 on the labour/install supply

Repair existing system

Often outside CIS (CISR14090 repair framing)

Soften VAT - repair may not be the same as qualifying install

If you quote supply-only and later add install under the same commercial relationship, revisit both CIS and VAT before the next invoice.

Domestic reverse charge note for contractor-paid heat pumps

Domestic reverse charge is a VAT rule between eligible VAT-registered construction businesses. It is not CIS and it is not a householder rule. When it applies to a standard-rated construction supply, you show VAT but the customer accounts for it - you do not collect the VAT as cash on that invoice. Full pattern: domestic reverse charge invoice UK.

Critical for heat pumps: if your residential install is correctly zero-rated under Notice 708/6, domestic reverse charge does not apply to that zero-rated supply. If the customer is a private householder, reverse charge does not apply anyway.

Worked examples A-D

Figures are ILLUSTRATIVE arithmetic only, not quotes, not UK average prices, not BUS grant amounts, and not a price list.

Example A - Householder ASHP on occupied home (no CIS, Notice 708/6 zero rate)

ILLUSTRATIVE. Assumes VAT-registered installer and a qualifying residential install meeting Notice 708/6 conditions within the 1 May 2023 to 31 March 2027 window.

Line

Amount (illustrative)

Labour - survey support, first fix, install, electrics, commission

£4,800

Materials - ASHP outdoor unit, cylinder, pipe, fittings, 8 radiators, controls

£6,200

Making good / waste

£350

Subtotal

£11,350

VAT at 0% (Notice 708/6 qualifying - illustrative assumption)

£0

Total

£11,350

CIS

None - private householder

If the install did not meet notice conditions, VAT would usually be standard-rated - do not force 0%.

Example B - Householder GSHP with deposit and stages (no CIS)

ILLUSTRATIVE. Householder; stages; VAT shown as 0% only as an illustrative Notice 708/6 assumption for a qualifying residential install.

Document

What it covers

Amount (illustrative)

Deposit invoice

Before loop materials / indoor plant order

£4,000

Stage - groundworks / first fix

Trenches, horizontal loops, first-fix pipe/electrics

£6,500

Stage - install / commission

Indoor plant, emitters, commission; less deposit credit

Balance of agreed package after deposit

VAT

0% if qualifying Notice 708/6; else as applicable

Soften - test facts

CIS

None - householder

-

Example C - Contractor-paid new ASHP install (verified 20% CIS)

ILLUSTRATIVE only. Verified subcontractor at 20%. Treat figures as VAT-exclusive for clarity. Assumes installation of a heating system (CISR14090 in scope), not a pure repair of an existing system.

Line

Amount

Labour (CIS-able)

£5,500

Materials you paid for (outdoor unit, cylinder, pipe, radiators, controls)

£7,800

Invoice total (ex VAT)

£13,300

CIS base (labour here)

£5,500

CIS deduction 20%

£1,100

Paid to you by contractor

£12,200 before any VAT treatment

Contractor remits CIS

£1,100

Do not claim free-issue plant as materials. Do not shrink labour by stuffing mark-up into materials. Soften VAT on the contractor invoice separately - residential qualifying zero rate, commercial standard rate, or reverse charge only where tests are met on standard-rated lines.

Example D - Materials-only delivery (no install)

Line

Amount (illustrative)

Supply ASHP outdoor unit and cylinder delivered to Plot 14

£5,400

Install

Not included

CIS

Generally outside if truly supply-only (CISR14220) - revisit if install is added under the same contract

VAT

Usually standard-rated supply without install

Mistakes that bounce heat pump invoices

Mistake

Why it bounces

Fix

"Heat pump done" one-liner

QS and householder cannot see type, capacity, emitters or stage

Name ASHP/GSHP/WSHP, capacity, cylinder/loop, emitters, stage

CIS on a householder bill

Wrong scheme actor

Remove CIS block for private customers

CIS on pure repair without checking CISR14090

Repair/maintenance of existing system often outside

Soften and test; do not auto-CIS every heating invoice

Reverse charge on a householder

Wrong VAT actor

Never reverse-charge private individuals

Reverse charge on a zero-rated 708/6 supply

Reverse charge does not apply to zero-rated lines

Use correct zero-rate narrative instead

Inventing 0% for hotel/commercial plant

Outside residential/charitable scope

Standard-rate unless another relief truly applies

Lump sum with no labour/materials split under CIS

Contractor cannot deduct correctly

Split labour and materials at direct cost

Free-issue unit claimed as your materials

Inflates materials, shrinks CIS base unfairly

Labour only on free-issue

No deposit credit shown

Client thinks they are being double-charged

Show deposit invoice number and credit

Invoice pretending to be MCS / Building Control / BUS paperwork

Not what an invoice is

Keep certificates and grant forms separate

Missing due date / payment route

Slow pay

Calendar due date + BACS and/or card link

Late payment: contractor debts are not consumer debts

Checked on 7 September 2026: Bank of England Bank Rate is 3.75% (held 30 July 2026; next MPC decision due 17 September 2026). For eligible business-to-business debts, statutory interest under the Late Payment of Commercial Debts framework is Bank Rate + 8% - currently 11.75% simple interest - plus fixed compensation of £40 / £70 / £100 per late invoice depending on debt size. Use the six-month reference date rule (rate in force on the preceding 31 December or 30 June). This statutory route does not automatically apply to private homeowners. See late payment rights and GOV.UK late commercial payments. InvoiceAdept does not file Money Claim Online or court claims.

How InvoiceAdept fits a heat pump installer

Need

InvoiceAdept

Same-day professional invoice from site

Yes - Free: five invoices/month

WhatsApp send to the householder thread

Pro £7.99 excl VAT

CIS labour/materials/rate lines

Pro+ £12.99 excl VAT

Card link (Stripe fees; no InvoiceAdept platform fee)

Available on plan

File CIS300 / VAT / MTD / Self Assessment

No - never

Issue MCS / Building Control / BUS paperwork

No - never

Operator: Tech Me Today Ltd, Companies House 15917255, ICO ZB944663. Start from the invoice generator or pricing.

FAQ

What should a UK heat pump invoice include?

Legal names and addresses, a unique number, dates, a description that names the site address, system type (ASHP/GSHP/WSHP), capacity, key plant and stage, quantities and rates, a due date and a way to pay. Split labour and materials on contractor jobs. VAT only if registered - including 0% with Notice 708/6 narrative when that genuinely applies. UTR and CIS only under a contractor, and only when CIS actually applies.

Do heat pump installers need a CIS invoice?

Only when a contractor is paying you for construction operations that are in scope. Lead with CISR14090 for heating-system installation. A homeowner job you sold yourself: no CIS. Soften for repair/maintenance of an existing system - often outside.

How do CIS deductions work on outdoor units, cylinders and loops?

CIS is on the labour / CIS base when the work is in scope. Units, cylinders, loop materials, pipe and radiators you paid for come off as materials at direct cost when evidenced. Rates are 20% verified, 30% unverified, 0% gross payment status. Mark-up is not a material. Free-issue is not your material.

Do I charge 0% VAT on every heat pump?

No. Qualifying residential (and relevant charitable) installs can be zero-rated under Notice 708/6 from 1 May 2023 to 31 March 2027 when conditions are met. Supply without install is usually standard-rated. Commercial installs outside scope should not be forced to 0%. InvoiceAdept does not decide VAT status.

Should I take a deposit before ordering the heat pump unit?

If your terms require it, yes - before you order outdoor units, cylinders or GSHP materials. Raise a numbered deposit invoice and credit it on later stages. See the deposit invoice template.

Is a boiler swap the same as a heat pump install for CIS?

Not always. CISR14090 distinguishes installation of a heating system (typically in) from repair/maintenance/alteration of an existing system and from replacing a boiler as a component (often out). Complete system replacement / new heat pump install is typically in when contractor-paid. Soften and test facts.

Does InvoiceAdept file CIS, VAT or Making Tax Digital to HMRC?

No. It raises the invoice, stores the record and on Pro+ prints CIS lines. It does not file CIS300, VAT returns or MTD quarterly updates. It does not issue MCS certificates, Building Control certificates or BUS grant paperwork.

What is the VAT registration threshold?

£90,000. Not £85,000.

What is the deemed CIS contractor construction-spend test?

More than £3 million on construction in the 12 months since the first payment for non-construction businesses - not £1 million. Mainstream construction contractors register when they pay subcontractors for construction work.

Can I reverse-charge a householder for a heat pump?

No. And reverse charge does not apply to zero-rated Notice 708/6 supplies either.

What payment terms should I use?

A practical residential default is 14 days from invoice date with a calendar due date. Commercial jobs follow the PO or contract. Put terms on the quote and the invoice.

Do I need MCS or Building Control on the invoice?

You can narrate that MCS certification, Building Control or BUS steps apply where relevant, but the invoice is not the certificate and not the grant form. Do not sell the PDF as statutory or scheme sign-off.

How should I invoice radiator upgrades or underfloor with the heat pump?

If emitters are in your package, show them as clear lines (labour and materials). If another trade invoices underfloor screed or finishes separately, do not pretend your heat pump invoice includes their whole package unless it does.

What if the main contractor free-issues the outdoor unit?

Invoice labour (and any materials you actually bought). Do not list free-issue plant as your materials for CIS.

Sole trader or limited company - does the template change?

Yes for the name block (personal name vs registered company name and number). CIS and VAT rules still follow the facts of the job and registration, not the template title.

Quote versus invoice on heat pump packages

A quote is the offer. An invoice is the request for payment for work done or a deposit due. Do not send a quote PDF labelled as an invoice when you want payment - accounts teams and householders need an invoice number, a due date and a tax point.

Document

Purpose

Typical timing

Quote / estimate

Scope, system type, capacity, emitters, price, terms

Before acceptance

Deposit invoice

Collect money before ordering unit / cylinder / loop kit

After acceptance, before order

Stage invoice

Design, first fix, groundworks or install milestone

When the stage trigger is met

Final / completion invoice

Balance, variations, deposit credits, snag close

Practical completion / handover

Retention release invoice

Release retained slice after the defects period

On the diary date in the contract

If the householder asks for a "receipt" after card payment, you can mark the invoice paid or issue a payment receipt - that is not a substitute for keeping the numbered invoice in your records.

MCS, Building Control and BUS - the invoice is not a certificate

Heat pump jobs often sit alongside MCS certification, Building Regulations notifications and Boiler Upgrade Scheme (BUS) vouchers or grants. Soften absolute claims here - scheme rules and local practice change, and grant amounts should be checked on current Ofgem / DESNZ publications rather than copied from a blog.

Topic

What the invoice can do

What it must not claim

MCS

Narrate that MCS-certified install / paperwork is part of the job if true

That the PDF is an MCS certificate

Building Control

Narrate application fee passed through if you charged it

That payment equals completion sign-off

BUS / grants

Note that a voucher or grant reference appears on client paperwork if factual

Invented grant amounts as "market facts"; InvoiceAdept does not issue BUS paperwork

F-gas / refrigerant

Keep compliance in your process notes

That the invoice is the F-gas register entry

Manufacturer warranty

State workmanship guarantee terms in plain English

Warranties you did not actually pass on

Keep certificates, vouchers and guarantee paperwork as separate attachments - the same habit as attaching a gas safety record to a boiler invoice rather than pretending the invoice is the record. Do not invent MCS statistics or current BUS grant figures on this page; check live Ofgem / DESNZ sources when you need numbers.

Variations that commonly appear on heat pump jobs

Price extras in writing before you install them. Then invoice them as coded variations so a dispute on one radiator run does not freeze the whole package.

Variation

Why it appears

Invoice tip

Extra radiators / larger emitters

Heat loss revisit after survey

V01 emitter schedule change

Add buffer tank

System volume / cycling concern

Separate plant line + labour

Underfloor zone added

Client wants UFH in extension

Manifold/zone as V-line

Consumer unit upgrade

Electrical capacity shortfall

Electrics labour + materials; or electrician's own invoice

Outdoor unit relocate

Planning / neighbour / noise concern after siting

Labour delta + any pad/bracket materials

Hot water cylinder upgrade

Capacity change mid-job

New materials line + labour; revisit deposit

Old boiler removal / disposal

Not in original scope

Clear strip-out line

Making good beyond allowance

Larger floor/wall openings

Variation with photos

Retention on contractor heat pump packages

Some main-contractor M&E packages hold a retention percentage until a defects date. If retention applies:

  • Show the full stage value, the retention withheld, and the net payable now

  • Diary the release date and raise a retention release invoice when due

  • Do not call retention a deposit

  • Do not assume householder jobs use retention - most do not

How to describe heat pump plant without sounding like a brochure

You do not need marketing copy. You need identifiers a QS can match to the quote.

Element

Useful invoice words

Avoid

ASHP outdoor unit

Capacity (kW), model if on PO, siting (side / rear / roof)

"Premium eco heating" with no capacity

GSHP array

Horizontal length or borehole count/depth as quoted

Vague "ground loops" only on a contractor bill

Cylinder / buffer

Type, capacity (litres) if quoted

Claiming free-issue cylinder as purchased materials

Emitters

Radiator count/sizes or UFH zones

Silent swap from radiators to UFH

Controls

Weather compensation, room stats, app gateway if included

"Smart controls" with no scope

Electrics

Dedicated circuit, isolator, CU work if in package

Whole-house electrical certificate package you did not deliver

Snagging and practical completion on heat pumps

Agree what "done" means before you ask for the final balance: system commissioned, hot water and heating demonstrated, controls explained, site left tidy, agreed snags listed. Photograph completion and keep commissioning records separate from the invoice. If a snag list remains, either hold a small agreed amount against those items or finish them before the final invoice - do not surprise a householder with a full balance while the outdoor unit still faults on defrost.

Checklist before you hit send

  • Unique invoice number and calendar due date

  • Correct legal customer (householder vs contractor Ltd name)

  • Site address and PO/plot if commercial

  • System type, capacity, key plant, emitters, stage

  • Deposit credits shown with prior invoice numbers

  • Labour/materials split if CIS applies

  • No CIS and no reverse charge on private householders

  • CIS tested against CISR14090 (install vs repair) when contractor-paid

  • VAT treatment matches registration and Notice 708/6 facts (0% only when qualifying)

  • No invented 0% on commercial out-of-scope jobs

  • Bank details and/or card link

  • UTR and CIS block only when required

  • MCS / Building Control / BUS narrative not sold as a certificate

  • Stripe UK cards 1.5%+20p if using card links; no InvoiceAdept platform fee

More worked detail: CIS materials evidence

When a contractor challenges your materials line, tickets win. Keep merchant or supplier invoices for outdoor units, cylinders, loop pipe, radiators and controls matched to the job address or PO. Round "about £7,000 materials" without evidence is how estimated deductions go against you. Van stock used on the job can sit in materials if you can show what it cost; guessing a round figure is weak.

More worked detail: householder communication channel

Domestic heat pump jobs are often sold in WhatsApp or email threads with photos of the plant cupboard and outdoor siting. Put the invoice in that same thread and keep the PDF numbered. Contractors still need email to accounts with the PO. Do not rely on a verbal "pay when the BUS comes through" after a five-figure plant order - grant timing is not your invoice due date unless your written terms say so.

About this guide

Written by InvoiceAdept Editorial for UK heat pump installers, heating engineers, plumbers, electricians and M&E subcontractors. Last reviewed 7 September 2026 against GOV.UK CIS pages (including CISR14090 as the lead heating-systems reference, plus CISR14220, CISR14240, CISR14020/14030, CISR15060/15090, and CISR14100 briefly for related fabric context), VAT Notice 708/6 (zero rate for qualifying residential/charitable heat pump installs from 1 May 2023 to 31 March 2027), VAT registration thresholds (£90,000), and Bank of England Bank Rate (3.75%, held 30 July 2026, next MPC 17 September 2026).

InvoiceAdept is invoicing software from Tech Me Today Ltd, Companies House 15917255, ICO ZB944663. Free: five invoices/month. Pro: £7.99 excl VAT. Pro+: £12.99 excl VAT with CIS lines. Stripe UK card fees apply (UK cards 1.5%+20p); InvoiceAdept adds no platform fee. InvoiceAdept does not decide CIS or VAT status and does not file CIS300, VAT returns, Making Tax Digital updates or Self Assessment. It does not issue MCS certificates, Building Control certificates or BUS grant paperwork.

Figures in examples are illustrative only. BUS grant amounts and MCS statistics are not invented here - check current Ofgem / DESNZ sources. This is general information, not tax, legal, Building Regulations, MCS, F-gas or grant advice.

Ready to get started?

InvoiceAdept helps UK tradespeople send invoices, track payments, and stay compliant — all from one place.

Start for free

No credit card required